Construction Updates – Mid June 2011
A few pictures from the construction progress in mid-June.
Summer 2011 SPIEL Now Available
In This Issue: – Chapter House Construction – Founder’s Day Weekend – Scholarship Awards [button link=”http://www.tnalpha.com/wp-content/uploads/2011/06/SpielSummer2011.pdf”]Download[/button]
June 2011 Construction Updates
In the last month, work has really started to bring things together at the SigEp house. Drywall was put up, the upper level was painted, and the center section was dried in. Exterior work included brick work, pouring the landscape beds in the back, and re-doing the L-Shaped room. Currently, they are building the walls […]
May 2011 Construction Updates
April brought the completion of the steel framing for the new center portion of the roof and portico. The goal for May is to have the building enclosed again and protected from the elements. Check out the pictures to see our progress.
Spring 2011 SPIEL Now Available
In This Issue: – House renovation – Founder’s Day Weekend – Scholarship and Building Fund Contributors – 2011 Planning Retreat [button link=”http://www.tnalpha.com/wp-content/uploads/2011/04/SpringSpiel2011.pdf”]Download[/button]
April 2011 Construction Updates
March construction on the SigEp House met some challenges with Mother Nature, but still continued at a steady pace. Much of the interior plumbing, networking and electrical were completed. Excavation of the grounds began, along with the footers for the new columns. The roof had been scheduled to be replaced in March, but due to […]